‘Parwan’ multipurpose irrigation project of Rajasthan will provide irrigation facilities in the following districts –
- (1)Jhalawar, Baran and Kota district
- (2)Tonk, Bundi and Kota district
- (3)Kota, Bundi and Jhalawar district
- (4)Jhalawar and Bhilwara district
Answer
Why
Correct — option (1), Jhalawar, Baran and Kota district.
Rajasthan's Economic Review 2020-21 describes Parwan in its section on water resources. It says the multipurpose irrigation project “Parwan” is under execution at district Jhalawar on the Parwan river.
It then says that, along with drinking water to 1,821 villages, “this project will provide irrigation facility in 2,01,400 hectare CCA in 637 villages of Jhalawar, Baran and Kota district.”
Those three districts, in that order, are option (1): Jhalawar, Baran and Kota district.
The idea to remember: Parwan project: built in Jhalawar on the Parwan river; irrigation for Jhalawar, Baran and Kota.
Why the others are wrong
- (2)Tonk, Bundi and Kota district — Only Kota is right. The option leaves out Jhalawar, where the project is being built, and Baran, and adds Tonk and Bundi, which the Economic Review does not name for Parwan's irrigation.
- (3)Kota, Bundi and Jhalawar district — Two of the three districts are right, but Bundi has taken Baran's place. The Review names the command villages as lying in Jhalawar, Baran and Kota.
- (4)Jhalawar and Bhilwara district — Jhalawar is right, but the option names only two districts and one of them is wrong. The Review gives three, Jhalawar, Baran and Kota; Bhilwara is not among them.
Concept
A multipurpose project uses the same water for more than one purpose. For Parwan, the Economic Review 2020-21 lists three: irrigation of 2,01,400 hectares of culturable command area, drinking water for 1,821 villages, and water for a thermal power project.
The Review says the project will provide 79 million cubic metres of water to the Thermal Power Project, which will produce electricity with a capacity of 2,970 megawatt.
The Review states the irrigated area as CCA, culturable command area: the cultivable land within the area a project commands.
RPSC's 2021 syllabus lists “Major Irrigation Projects & Water Conservation Techniques” under the Geography of Rajasthan.
The Review lists Parwan among seven major irrigation projects in progress in 2020-21, alongside the Narmada Canal Project, Dholpur lift and Navnera Barrage (ERCP), among others. It records a revised sanction of ₹7,355.23 crore and says the project is proposed to be completed in 2023.
Rajasthan's Budget at a Glance 2021-22 provides ₹885 crore for the Parwan Project.
Key facts
- Economic Review 2020-21: Parwan multipurpose irrigation project is under execution in Jhalawar district, on the Parwan river.
- Irrigation for 2,01,400 hectare CCA in 637 villages of Jhalawar, Baran and Kota districts; drinking water to 1,821 villages.
- 79 million cubic metres of water planned for a Thermal Power Project of 2,970 MW capacity.
- Revised administrative and financial sanction ₹7,355.23 crore; ₹446 crore spent in 2020-21 up to December 2020.
- Budget at a Glance 2021-22: ₹885 crore provided for the Parwan Project.
Source: Rajasthan Economic Review 2020-21, Agriculture & Allied Sectors chapter, Water Resources section.
Study next
Common traps
- Swapping in Bundi: the Review names Jhalawar, Baran and Kota for Parwan's irrigation, and Bundi is not among them.
- Stopping at the site district: the project is built in Jhalawar, but its irrigation reaches Baran and Kota too.
- Counting the districts wrongly: the Review names three districts, not two.
A question can name an irrigation project and ask which districts it will irrigate, with other districts swapped in the options.
A question can also match several projects to their beneficiary districts, or ask the district where a project is being built.
Related PYQs
UnlockIAS will link similar questions from RAS Pre 2018 here once that paper is published on this site.
Practice
- practice — not a real PYQ
According to Rajasthan's Economic Review 2020-21, the Parwan multipurpose irrigation project is under execution in which district?
- (a)Jhalawar
- (b)Baran
- (c)Kota
- (d)Bundi
Answer(1) — The Review says it is under execution at district Jhalawar. Options (2) and (3) receive its irrigation but are not where it is being built, and option (4) is not named. - practice — not a real PYQ
Rajasthan's Economic Review 2020-21 says the Parwan project will provide water to a thermal power project. The quantity it gives is
- (a)79 million cubic metres
- (b)7.9 million cubic metres
- (c)790 million cubic metres
- (d)2,970 million cubic metres
Answer(1) — The Review gives 79 million cubic meters. Options (2) and (3) shift the decimal place, and option (4) borrows the 2,970 figure, which is the power project's capacity in megawatt.