A completes 2⁄3 of a certain job in 6 days. B can complete 1⁄3 of the same job in 8 days and C can complete 3⁄4 of the job in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
This question appeared in the PPSC Prelims 2021 examination (GS-II). It is Question 46 out of 80 questions in this paper.