A and B working together can finish a piece of work in 4 days while A alone can do it in 6 days. Then the number of days that B can take to complete the work is :
Correct Answer: (a)
Official keyThis question appeared in the NPSC Prelims 2018 examination (GS). It is Question 58 out of 200 questions in this paper.