Consider the following statements regarding the new railway line in Mizoram: (i) It connects Bairabi with Sairang. (ii) The total length of the new railway line is 101 kms. (iii) The project is divided into four sections – Bairabi-Hortoki, Hortoki-Kawnpui, Kawnpui-Mualkhang, and Mualkhang-Sairang. (iv) The Commission of Railway Safety (CRS) has recently approved the opening of the railway line from Hortoki to Sairang in Mizoram. Which of the above statements are correct?
Correct Answer: (c)
Official keyThis question appeared in the MZPSC Prelims 2025 examination (GS). It is Question 2 out of 100 questions in this paper.
This question was part of the MZPSC Prelims 2025 (GS). The MZPSC Prelims examination tests candidates on general studies, current affairs, and aptitude through multiple-choice questions.