One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days, working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they were willing to work only 8 hours a day. With this much labour, in how many days would he be able to complete the same job?
This question appeared in the HPSC Prelims 2023 examination (CSAT). It is Question 10 out of 200 questions in this paper.
This question was part of the HPSC Prelims 2023 (CSAT). The HPSC Prelims examination tests candidates on general studies, current affairs, and aptitude through multiple-choice questions.
Practice previous year questions from all HPSC Prelims papers and compare patterns with UPSC Prelims PYQ to identify overlapping topics.