Two workers M and N are engaged to do a work. M working alone takes 8 hours more to complete the work than if both worked together. If N worked alone, he would need 4.5 hours more to complete the task than they both work together. What time will they take to complete the work together?
This question appeared in the GPSC Prelims 2018 examination (GS). It is Question 191 out of 397 questions in this paper.