Dhaval and Dhiraj together can do a piece of work in 12 days. Dhaval alone can do it in 20 days. In how many days can Dhiraj alone do it?
- (a)30
- (b)28
- (c)29
- (d)27
Answer
Why
Correct — A. Turn each time into a one-day rate, then subtract.
Together, per day = 1⁄12 of the work
Dhaval alone, per day = 1⁄20
Subtract: 1⁄12 − 1⁄20 = 5⁄60 − 3⁄60 = 2⁄60 = 1⁄30
Dhiraj does 1⁄30 of the work a day, so he takes 30 days → option (a)
Why the others are wrong
- (b)28 — 1⁄20 + 1⁄28 = 3⁄35, so with a 28-day Dhiraj the pair would finish in 35⁄3 ≈ 11.7 days, faster than the 12 in the stem.
- (c)29 — 1⁄20 + 1⁄29 = 49⁄580, a joint time of 580⁄49 ≈ 11.8 days. Only a 30-day Dhiraj makes the pair take exactly 12.
- (d)27 — 1⁄20 + 1⁄27 = 47⁄540, a joint time of about 11.5 days. A faster Dhiraj pulls the pair below the stated 12.
Concept
Days do not add or subtract; rates do. Someone who finishes a job in n days does 1⁄n of it each day.
Combined rate − known rate = unknown rate, then flip the rate back into days.
The LCM method does the same with whole numbers. Take the work as LCM(12, 20) = 60 units: together they do 5 units a day, Dhaval 3, so Dhiraj does 2, and 60 ÷ 2 = 30 days.
All four options lie between 27 and 30 days, so estimating will not separate them. The fraction arithmetic has to be done.
Key facts
- Rate = 1 ⁄ time: a job done in 20 days means 1⁄20 of it per day.
- Rates of people working together add, so an unknown rate = combined rate − known rate.
- B alone = (A × T) ⁄ (A − T), where A is A's time alone and T the joint time: 20 × 12 ⁄ 8 = 30.
Study next
Common traps
- Subtracting the days: 20 − 12 = 8 is neither a rate nor the answer.
- Adding the rates instead of subtracting: 1⁄12 + 1⁄20 = 2⁄15 gives 7.5 days, faster than the pair.
The same subtraction of rates solves 26 Sep 2024, 12:30, Quant Q.9: Varun and Raju together take 40 hours and Varun alone 50, so Raju's rate is 1⁄40 − 1⁄50 = 1⁄200 and he needs 200 hours.
Related PYQs
No directly related past PYQ was found.