Sameer can complete a work in 16 days. In how many days will the work be completed by Ajay, if his efficiency is 60% more than that of Sameer?
- (a)12 days
- (b)10 days
- (c)13 days
- (d)15 days
Answer
Why
Correct — B. For the same work, time is inversely proportional to efficiency.
Sameer's efficiency = 100, so Ajay's = 100 + 60 = 160
Efficiency ratio Sameer : Ajay = 100 : 160 = 5 : 8
Time ratio is the reverse: 8 : 5
Ajay's time = 16 × 5⁄8 = 10 days → option (b)
Check in units: work = 16 × 5 = 80 units, Ajay does 8 a day, 80 ÷ 8 = 10.
Why the others are wrong
- (a)12 days — 12 days means Ajay works 16⁄12 = 4⁄3 as fast, only 33⅓% more efficient than Sameer, not 60%.
- (c)13 days — 13 days makes Ajay 16⁄13 ≈ 1.23 times as fast, about 23% more efficient. A 60% edge cuts the time further: 16 ÷ 1.6 = 10.
- (d)15 days — 15 days makes Ajay only 16⁄15 ≈ 1.07 times as fast, about 6.7% more efficient, far short of 60%.
Concept
For a fixed job, work = efficiency × time. Hold the work constant and efficiency and time move in opposite directions by the same factor.
60% more efficient means efficiency × 1.6, so time ÷ 1.6. It does not mean the time is cut by 60%.
16 ÷ 1.6 = 10 days, a 37.5% cut in time: 60 ÷ 160 = 0.375.
Key facts
- Work = efficiency × time
- For the same work, time is inversely proportional to efficiency
- If efficiency rises by r%, time falls by r ÷ (100 + r) × 100%: here 60 ÷ 160 = 37.5%
Study next
Common traps
- Cutting the time by 60% (16 × 0.4 = 6.4 days) instead of dividing it by 1.6
- Multiplying the time by 1.6 (25.6 days), as if more efficiency meant more days
Also asked 12 Sep 2025, 12:30, Quant Q.14: efficiencies 5 : 2 and P takes 12 days, so Q takes 12 × 5⁄2 = 30 days.
The inverse rule runs pipes at 26 Sep 2024, 09:00, Quant Q.21: one pipe fills four times as fast as the other, and the slower one alone takes 240 minutes.
Related PYQs
No directly related past PYQ was found.