The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?
- (a)24 days
- (b)30 days
- (c)35 days
- (d)40 days
Answer
Why
Correct — B. For the same job, time is inversely proportional to efficiency.
Efficiency P : Q = 5 : 2
Invert for time: P : Q = 2 : 5
P's 2 parts = 12 days → 1 part = 6 days
Q's 5 parts = 5 × 6 = 30 days → option (b)
Why the others are wrong
- (a)24 days — 24 days is 12 × 2, the time for a worker half as efficient as P. Q's efficiency is 2⁄5 of P's, so Q takes 5⁄2 as long: 30 days.
- (c)35 days — 35 days would make the time ratio 12 : 35, so the efficiency ratio would be 35 : 12, not 5 : 2.
- (d)40 days — 40 days gives a time ratio of 12 : 40 = 3 : 10, which means efficiencies of 10 : 3, not 5 : 2.
Concept
Efficiency is work done per day. For a fixed job, doubling efficiency halves the time, so times run in the reverse ratio of efficiencies.
A units check gives the same answer: call P's daily work 5 units, so the job is 5 × 12 = 60 units. Q does 2 units a day and needs 60 ÷ 2 = 30 days.
Key facts
- Work = efficiency × time, so for a fixed job efficiency × time is constant.
- An efficiency ratio a : b means a time ratio b : a.
- Here 5 × 12 = 2 × t, so t = 60 ÷ 2 = 30 days.
Study next
Common traps
- Multiplying 12 by 2⁄5 instead of 5⁄2 gives 4.8 days: the less efficient worker would then finish faster, which cannot be right.
The reverse-ratio step appears with pipes on 26 Sep 2024, 16:00, Quant Q.7: B fills twice as fast as A and together they take 45 minutes, so A alone takes 3 × 45 = 135 minutes.
On 26 Sep 2024, 09:00, Quant Q.21 one pipe is four times as fast as the other and together they take 48 minutes, so the slower alone takes 5 × 48 = 240 minutes.
Related PYQs
No directly related past PYQ was found.