A & B together earn ₹840 for a job. A works the whole time; B joins after the job is 25 % done. B is twice as efficient as A. Find B’s share.
- (a)₹ 420
- (b)₹ 300
- (c)₹ 360
- (d)₹ 400
Answer
Why
Correct — A.
Rates: A = 1 unit per day, B = 2 units per day (twice as efficient)
First 25% of the job: A alone, so A does 25%
Last 75%: A and B together, split 1 : 2
A's part = 1⁄3 × 75% = 25%, B's part = 2⁄3 × 75% = 50%
Totals: A = 25% + 25% = 50%, B = 50%
Pay follows work: B = 50% of ₹840 = ₹420 → option (a)
Why the others are wrong
- (b)₹ 300 — ₹300 is 5⁄14 of ₹840, but B did exactly half the job, and pay is split in the ratio of work done.
- (c)₹ 360 — ₹360 is 3⁄7 of ₹840, a 4 : 3 split by time on the job (A all of it, B 75%) at equal rates. That reads '25 % done' as a quarter of the time and ignores B's double speed.
- (d)₹ 400 — ₹400 is 10⁄21 of ₹840, a little under half. B's work comes to exactly 50% of the job, so B's share is exactly ₹420.
Concept
Wages follow work done, and work done = rate × time. B's higher efficiency counts only for the part of the job B was present for.
Split the job at the moment B joins. A alone finishes the first 25%. For the remaining 75% both work, and at rates 1 : 2 that stretch divides into 25% for A and 50% for B.
A ends with 50% of the job and B with 50%, so the ₹840 splits equally.
Key facts
- Pay for a shared job is divided in the ratio of work done
- Work done = efficiency × time
- When rates are 1 : 2, a joint stretch of work divides 1⁄3 : 2⁄3
Study next
Common traps
- Splitting ₹840 in the efficiency ratio 1 : 2, which gives B ₹560 and ignores A's solo first quarter
- Reading 'after the job is 25 % done' as 25% of the time rather than 25% of the work
The efficiency-to-rate step also decides 15 Sep 2025, 12:30, Quant Q.12, where A is 'three times more efficient' than B and the key, 22.5 days, reads that as a 3 : 1 rate.
Related PYQs
No directly related past PYQ was found.