Q: A construction work is to be completed in 46 days by 117 men at work, 8 hours being the working period per day. After 33 days, it is found that only 3⁄4 of the work is completed. If the working time is increased to 9 hours/day, the number of additional men required to complete the work in 46 days period will be
(a)72 men
(b)81 men
(c)90 men
(d)99 men
Correct Answer: (a)