Q: In Network Computation Process, which one of the following is correct for forward pass?
(a)It starts with the first project activity(ies) and traces each path (chain of sequential activities) through the network to the last project activity(ies)
(b)This is the longest path in the network, which will delay the project
(c)It starts with the last project activity(ies) on the network
(d)It starts with the last project activity(ies) and traces each path (chain of sequential activities) through the network to the first project activity(ies)
Correct Answer: (b)